Founders Parkway


This work will occur in five phases, with a mid-project break for the holidays. Before the holiday break is scheduled to start on Nov. 19, all work between Trail Boss Drive and Maleta Lane is expected to be complete. Work will begin again on Jan. 12, 2015 and is expected to last until July 2015.

Work hours will be 7 a.m. to 7 p.m. daily (including weekends). 

Traffic will be down to one lane in each direction between I-25 and Allen Way on Founders Parkway as part of CDOT’s work to reconstruct the roadway, starting April 7. Alternate routes are advised.

In addition, left turns at Allen Way for both eastbound and westbound traffic will be closed.

These closures are expected to last about seven weeks.

We know this will have an impact on your commute, and we appreciate your patience and care as you drive through this construction zone. Once this is complete, the majority of CDOT’s project will be done. Drive safely!

This article originated from http://www.crgov.com/index.aspx?NID=1530