Current Schedule


Construction Schedules for 2015 Pavement Maintenance Program

Activity Location Earliest start date Completed
Concrete removal and replacement Downtown Castle Rock May 18 June 12
 Asphalt patching Downtown Castle Rock April 20  June 19
 Overlay Metzler, Woodlands, Red Hawk and Castle North April 30  June 26
 Asphalt reconstruction Canyon Drive, Gigi Street and Sunset Court April 20  


Activity Location Earliest start date
Completed
Asphalt patching Metzler, Woodlands, and Red Hawk

May 11

Slurry seal Metzler, Woodlands, Red Hawk and Castle North June 1  
Activity Location Earliest start date
Completed
Remove and replace curb, gutter and sidewalk Red Hawk Neighborhood April 30
 Tentative construction schedule for 2015 Plum Creek Boulevard Reconstruction Project
Activity Location Earliest start date Completed
Reconstruction  

Plum Creek Blvd (Emerald Drive to Castlemain Place)

May 11  
Tentative construction schedule for 2015 Concrete Restoration Project
Activity Location Earliest start date Completed
Concrete restoration


N. Meadows Dr. from Meadows Blvd to Butterfield Crossing Boulevard

            July 15

 

Tentative construction schedule for 2015 Emulsified Seal Coat Program
Activity Location Earliest start date Completed
Emulsified seal coat

N/A

N/A N/A
Tentative construction schedule for 2015 Asphalt Rejuvenating Agent Project
Activity Location Earliest start date Completed
Asphalt rejuvenating

Metzler and Red Hawk

TBD

TBD

This article originated from http://www.crgov.com/index.aspx?NID=947
This post was originally published on this site


This post was originally published on this site
  1. No comments yet.
(will not be published)